ODE Sistem Application Details
![]() |
1. The surfaces, which will undergo ODE SISTEM application for the first time, must be smoothened first with rough plaster. All surfaces are cleared from any swollen plaster or paint residues, dirt, dusts and grease. |
![]() |
2. Sub basement grade of the building, which is the level of starting for ODE Isıpan BD thermal insulation boards is marked throughout the building girth with a water balance. 3. Then sub basement promeshs, which were selected in accordance with the thicknesses of insulation Boards, are fixed to the wall by leaving expansion joints of 0.5 - 1 cm. |
![]() |
4. 25 kg of ODE SISTEM Bonding Mortar - Yapfix is added slowly to the water of approximately ~6.25 kg; and then mixed using a mixer with a speed of 400-600 cycles per minute until a uniform and smooth mixture is derived, ranging from 3 to 5 minutes. It is rested approximately for 3 to 5 minutes and then remixed for 30 seconds. No materials other than mixing water should be added to the mixture. Application should coincide with hours that do not receive direct sun or wind especially in warm weather. |
![]() |
5. Prepared mixture is applied continuously throughout the edges of the Board with steel trowel or in groups in mid sections of the board in ODE Is›pan BD applications, depending on the smoothing status of the building structure. Bonding mortar can be applied to the thermal insulation Board with the help of a comb trowel in very smooth surfaces. Consumption is 5 kg/m2. |
![]() |
6. ODE Isıpan BD thermal insulation boards are bonded to the wall surface by fitting horizontally into sub basement promeshs. Then the rows are bonded in the balance in tusk principle. Mechanical mixture of the Boards by using ODE SISTEM Premium dowells occur at least 24 hours after the bonding process. |
![]() |
7. Number of dowells is 6 per m2. It is adjusted to have one on the corners of the Board and two in the middle of the board. Corner dowells are used in points where the boards overlap. The number of dowells is increased especially in high storey buildings and building corners; and two dowells are applied for each Board to the corners. |
![]() |
8. ODE SISTEM Reinforced PVC Corner Promesh is placed in order to ensure the impact resistance of corner points. |
![]() |
9. 20 kg of ODE SISTEM Plaster Mortar - Sivamix is added slowly to the water of approximately ~4.60 kg; and then mixed using a mixer with a speed of 400-600 cycles per minute until a uniform and smooth mixture is derived, ranging from 3 to 5 minutes. It is rested approximately for 3 to 5 minutes and then remixed for 30 seconds. ODE SISTEM Plaster Mortar - Sıvamix is applied one coat with the help of a steel trowel. In order to achieve a homogenous thickness, it is leveled on the plaster Board with a comb trowel of 3x3 mm. ODE SISTEM Svaf is held by pressing gently. 10 cm is overlapped in vertical and horizontal fittings of the net. |
![]() |
10. Second coat plaster is applied after the discharge of plaster water to an extent, which will prevent the embedding of the net, and the process is completed. Total consumption in two coat plaster application is 5 kg/m2. |
![]() |
11. ODE SISTEM application is completed with a final coat application. Either Ode SISTEM decorative mineral plaster and paint or decorative coating is applied as the final phase after the set of the second coat plaster; and the intended appearance is achieved. |